2025 Maintenance & Construction Schedule
Revised November 4, 2025
This list contains planned road construction projects. Please note dates are approximate, and actual construction time frames are subject to change. New updates and completed projects are shown in bold.
County Maintenance Activities
- May 27, 2025 to June 10, 2025: Grader Blade Patching various locations
- May 5, 2025 to June 27, 2025: Seal Coat (Chip and Scrub Seal) 32 Miles
- Flaggers with 35 MPH Speed Reduction Zones
- Prep work will start May 5, 2025
- CTH H (City of Stanley 1st Ave to 8th Ave.) 0.5 Miles - Completed
- CTH H (City of Stanley STH 29 West Ramp to Maple St) 0.4 Miles - Completed
- CTH O (City of Stanley Maple St to Deer Park Rd) 0.7 Miles - Completed
- CTH X (184th St to CTH K North) 1.3 Miles - Completed
- CTH OO (USH 53 to CTH P) 1.3 Miles - Completed
- CTH X (CTH F to 90th St ) 1.6 Miles - Completed
- CTH X (CTH T to CTH F) 1.5 Miles - Completed
- CTH F (CTH S to CTH X ) 4.3 Miles - Completed
- CTH N (Elk Creek to 40th St) 0.4 Miles - Completed
- CTH A (CTH DD South to 40th St) 1.0 Mile - Completed
- CTH DD (186th Ave to STH 64) 1.8 Miles - Completed
- CTH AA (202nd Ave to 226th Ave) 2.4 Miles - Completed
- CTH S (139th Ave to CTH Y) 0.3 Miles - Completed
- CTH S (115th Ave to 139th Ave) 2.7 Miles - Completed
Construction Projects
Culvert Pipe Replacements - Daily Closures (No Signed Detours)
- CTH SS (Village of New Auburn) - Completed
- CTH O (CTH XX - STH 27) - Completed
- CTH X (West of 270th) - Completed
- County Maintenance Culvert Pipe Replacements (Various Locations) July 7, 2025 to July 31, 2025
Paving Projects
CTH M (CTH F (North) to STH 40) 2.5 Miles
- Flaggers with lane closures
- Pulverize - Completed
- Pave Binder - Completed
- Pave Surface - Completed
- Shoulder - Completed
- Paint - Completed
CTH F (CTH M to 280th Ave) 1.95 Miles
- Flaggers with lane closures
- Pulverize - Completed
- Pave Binder - Completed
- Pave Surface - Completed
- Shoulder - Completed
- Paint - Completed
CTH E (STH 64 to CTH Z) 3.4 Miles
- Flaggers with lane closures
- Pulverize - Completed
- Pave Binder - Completed
- Pave Surface - Completed
- Shoulder - Completed
- Paint - Completed
CTH H (Polley Lane to STH 64) 1.4 Miles
- Flaggers with lane closures
- Pulverize - Completed
- Pave Binder - Completed
- Pave Surface - Completed
- Shoulder - Completed
- Paint - Completed
CTH M (USH 53 to New Pavement (New Auburn)) 0.3 Miles
- Flaggers with lane closures
- Milling - Completed
- Pave Surface - Completed
- Shoulder - Completed
- Paint - Completed
CTH X (STH 27 to 270th St (Cadott)) 1.0 Miles
- Village of Cadott Utility Work - Completed
- Milling - Completed
- Pave Surface - Completed
- Shoulder - Completed
- Paint - Completed
CTH OO (Hogarth to STH 124 (Lake Hallie)) 2.0 Miles - Completed
CTH J & 50th Avenue Intersection - Completed
Bridge Projects
CTH M Over Big Elk Creek Bridge Replacement in Town of Wheaton - Completed
CTH G Over Yellow River Bridge Replacement in Town of Colburn - Completed
- Bridge opened to traffic October 31, 2025.
CTH M Over Mud Creek Bridge Replacement in Town of Sampson - Completed
CTH Q Over Tilden Creek Bridge Deck Replacement in Town of Tilden - Completed
- Bridge opened to traffic October 31, 2025.
Chippewa County Highway State Maintenance Projects
May / June
- Sweeping - Completed
- Annual bridge washing and deck sealing on various State and County bridges
- Flaggers with lane closures - Completed
- Concrete Repairs STH 29 (Various Locations) - Completed
- Daily Lane and Shoulder Closures
- Shouldering #2 State Roads (Various Locations) - Completed
Wisconsin State Road Construction Impacts
Northwest Wisconsin Weekly Construction Updates
The Chippewa County Highway Department would like to keep you informed of all projects being completed in Chippewa County. Get state construction and road condition updates.